Date | Project |
---|---|
Dec 06 | Bathymetric & sub bottom profiling survey to ascertain position & depth of approx 7km of 40’ gas pipeline. |
Dec 06 | Pipeline as laid & post backfill surveys at Taweelah, for part of the “Dolphin” project. |
Dec 06 | Supply of personnel & positioning equipment & navigation software for sub bottom profiling & vibrocoring works. |
Dec 06 | Assistance with bathymetric survey of power & desalination plant intakes & outfalls at Umm Al Nar. |
Nov06-Sept07 | Lease of survey vessel for dredging project in Bandar Abbas Iran. |
Nov 06 | Calibration of Ships GPS & Gyrocompass prior to offshore works. |
June06-May07 | Survey support and consultancy for the Al Reem “Shams” dredging & reclamation project, conducting bathymetric, & topographic surveys and some earthworks supervision. |
Nov 06 | Sub Bottom Profiling Survey. |
Oct 06 | Calibration of ships GPS and Gyrocompass prior to offshore works. |
Oct 06 | Lease of survey equipment & software for bathymetric survey in Oman. |
Sept 06 | Post dredge survey of Boskalis jetty & approach channel in Mussafah |
Sept 06 | Bathymetric & topographic survey for “Sadiyat Island” development. |
Sept 06 | Calibration of ships GPS and Gyrocompass prior to offshore works. |
Sept 06 | Lease of survey launch, crew, surveyor & navigation system to assist with sub bottom profiling survey. |
Sept 06 | Monitoring of dredging works carried out by UIB Co. subcontractor. Bathymetric survey on completion of dredging. |
Sept 06 | Geodetic calculations for “Coconut Island” project setting out. |
Sept 06 | Geotechnical investigation using washbore equipment. |
Sept 06 | Calibration of Ships GPS & Gyrocompass prior to offshore works. |
Aug 06 | Bathymetric survey for dredging works at new jetty in Mussafah. |
Aug 06 | Calibration of ships GPS and Gyrocompass prior to offshore works. |
Aug 06 | Buried gas pipeline search using sub bottom profiling equipment. |
July 06 | Calibration of ships GPS and Gyrocompass prior to offshore works. |
July 06 | Pre construction bathymetric survey of the offshore section of the “Nujoom Island” project in Umm Al Quwain. |
July 06 | Post dredge bathymetric survey & volume calculations at Masnooah Island. |
July 06 | Interim survey of dredging works at Masnooah Island. |
June/Jul 06 | Buoy positioning for intake/outfall works at the “Atlantis Hotel” project on Palm Jumeirah. |
June 06 | Interim Survey of dredging works at Masnooah Island |
June 06 | Bathymetric & Topographic survey of the proposed “Fantasy Island” project location |
June 06 | Consultancy & market research into the Middle East dredging industry |
June 06 | Post dredge bathymetric survey & volume calculations at Qarasina Island. |
May 06 | Dense sounding bathymetric check at Qarasina Island. |
May 06 | Supply of tide & wave monitoring instruments for “Reem Island” project. |
May 06 | Pre Dredge Bathymetric & topographic survey at private palace area at Taweelah. |