Date Project
Dec 06 Bathymetric & sub bottom profiling survey to ascertain position & depth of approx 7km of 40’ gas pipeline.
Dec 06 Pipeline as laid & post backfill surveys at Taweelah, for part of the “Dolphin” project.
Dec 06 Supply of personnel & positioning equipment & navigation software for sub bottom profiling & vibrocoring works.
Dec 06 Assistance with bathymetric survey of power & desalination plant intakes & outfalls at Umm Al Nar.
Nov06-Sept07 Lease of survey vessel for dredging project in Bandar Abbas Iran.
Nov 06 Calibration of Ships GPS & Gyrocompass prior to offshore works.
June06-May07 Survey support and consultancy for the  Al Reem “Shams” dredging & reclamation project, conducting bathymetric, & topographic surveys and some earthworks supervision.
Nov 06 Sub Bottom Profiling Survey.
Oct 06 Calibration of ships GPS and Gyrocompass prior to offshore works.
Oct 06 Lease of survey equipment & software for bathymetric survey in Oman.
Sept 06 Post dredge survey of Boskalis jetty & approach channel in Mussafah
Sept 06 Bathymetric & topographic survey for “Sadiyat Island” development.
Sept 06 Calibration of ships GPS and Gyrocompass prior to offshore works.
Sept 06 Lease of survey launch, crew, surveyor & navigation system to assist with sub bottom profiling survey.
Sept 06 Monitoring of dredging works carried out by UIB Co. subcontractor. Bathymetric survey on completion of dredging.
Sept 06 Geodetic calculations for “Coconut Island” project setting out.
Sept 06 Geotechnical investigation using washbore equipment.
Sept 06 Calibration of Ships GPS & Gyrocompass prior to offshore works.
Aug 06 Bathymetric survey for dredging works at new jetty in Mussafah.
Aug 06 Calibration of ships GPS and Gyrocompass prior to offshore works.
Aug 06 Buried gas pipeline search using sub bottom profiling equipment.
July 06 Calibration of ships GPS and Gyrocompass prior to offshore works.
July 06 Pre construction bathymetric survey of the offshore section of the “Nujoom Island” project in Umm Al Quwain.
July 06 Post dredge bathymetric survey & volume calculations at Masnooah Island.
July 06 Interim survey of dredging works at Masnooah Island.
June/Jul 06 Buoy positioning for intake/outfall works at the “Atlantis Hotel” project on Palm Jumeirah.
June 06 Interim Survey of dredging works at Masnooah Island
June 06 Bathymetric & Topographic survey of the proposed “Fantasy Island” project location
June 06 Consultancy & market research into the Middle East dredging industry
June 06 Post dredge bathymetric survey & volume calculations at Qarasina Island.
May 06 Dense sounding bathymetric check at Qarasina Island.
May 06 Supply of tide & wave monitoring instruments for “Reem Island” project.
May 06 Pre Dredge Bathymetric & topographic survey at private palace area at Taweelah.